home - Govt. Agencies & Policies - Central Govt. Policies - MNRE Guidelines

 

MNRE Guidelines :


No.66/53/2006-WE

Government of India

Ministry of New and Renewable Energy

(Wind Power Division)

                                                                Block No.14, CGO Complex,

                                                             Lodhi Road, New Delhi - 110003

                                                                                    Date : 08/01/2010

 

Sub: Revised Guidelines for Wind Power Projects – Self Certification regarding.

 

In partial modifications to the Ministry’s Circular of even number dated 08.12.2009 regarding the above mentioned subject, the following modifications / changes have been incorporated:

 

(i) The Page no. 2, Para 2 (i) (a) – shall now be read as under:

 

 

a. Qualifying criteria*

·         Having own manufacturing facility in India and is in operation for

past five years.

or

   Has a track record of installation of atleast 100 MW wind power

  projects in India.

 

·         Has obtained ISO-9001 certificate and has capacity to provide full fledged after sales service.

 

·         Atleast one model has been tested and certified by C-WET or any recognized international agency.

 

*The decision of C-WET/ Revised List of Models and Manufacturers (RLMM)committee shall be final on the matter.

 

 

 (ii) The Page no. 2, Para 2 (i) (b) – shall now be read as under:

 

b.      Number of machines allowed to be installed

 

The existing manufacturers shall be permitted to install and commission.

50 no. of machines on commercial basis from the date of signing of agreementfor type testing and certification with C-WET / internationally accredited type testing and certifying agency after completing the requirements as given in the

 

Technical note to be prepared by C-WET – Refer Para 1 (i) above.

 

(iii) The Page no. 3, Para 2 (ii) (b) – shall now be read as under:

b.      Number of machines allowed to be installed

 

The new manufacturer shall be permitted to install and commission. 20 no.of machines on commercial basis from the date of signing of agreement for type testing and certification with C-WET / internationally accredited certifying agency after completing the requirements as given in the Technical note to be prepared by C-WET – Refer Para 1 (i) above.

 

(iv) The Page no. 3, Para 3 – a additional point has been included which is as under:

           

(iii) “Wind turbine models for which type testing and

certification agreements signed with C-WET based on

the earlier MNRE guidelines no.66/53/2006-WE dated

24.07.2008, the conditions stipulated therein shall be

followed.”

 

(v) The Page no. 4 (Annexure), Para 1 – shall now be read as under:

 

This guideline document is applicable for the Indian Wind Turbine Manufacturers those who sign the projects for the Type Testing and Certification either by themselves or by their collaborators under the recognized Type Certification schemes (in vogue) as per TAPS-2000 (amended) with any International Accredited Type Testing and Certification Body other than C-WET and seeking inclusion in RLMM

list under Self Certification as per the MNRE guidelines.

 

(vi) The Page no. 4 (Annexure), Para 2 – shall now be read as under:

 

2.  After signing the agreement, the wind turbine manufacturer shall submit all the required documentation for Type Certification within the time schedule or extension, if any as per the MNRE guidelines. However, atleast all the documents shall be submitted within six months period, except type test reports. The wind turbine manufacturer shall submit a letter issued by the Type Certification Body regarding the

status of submission of the all the required documentation for Type Certification within the time schedule or extension, if any. Similarly, a letter issued by the type testing body regarding the status of type testing shall be submitted.

 

2. The other provisions / terms and conditions mentioned in the Guidelines no. 66/53/2006-WE dated 08.12.2009 on the subject shall remain unchanged. This issues with the approval of the competent authority.

 

 

(G. UPADHYAY)

Director

To

All concerned.